Keywords:
Sl. No. | Name of Project | Employer | Funded by | Date of | Date of | Value of Executed |
---|---|---|---|---|---|---|
1 | Improvement of Jatrabari Intersection (including Equria-Babubazar link road) to Patchchar-Bhanga through Mawa road of Dhaka-Khulna (N-8) highway to 4 lane with separate lane for slow moving vehicle Project, Package - 06 | BD Army | GOB | May-17 | Dec-20 | 7,972,033,242.62 |
2 | Dedging work by Cutter Section dredger and construction tarza walling by bamboo piling and earthen dype for developing navigability in the river Meghna Pagla Buri of Chitra-Nabinagar-Gokernaghat river route | BD Army | GOB | Oct-18 | Sep-19 | 176,760,000.00 |
3 | Widening of Fulchari Link Road and Saghata Bazar (2.00 km), Reconstruction of 3 Nos (37m) RCC Culvert/Slab Bridge at 5th, 25th & 27th km, Protective and Earthwork of Gaibandha - Fulchari - Bharatkhali - Saghata Road (Z-5552) under Road Division, Gaibandha during the year 2017-2018. Contract No. eGP-34/RHD/ACE/RZ/2017-2018 (ID No. 190984). | RHD | GOB | May-18 | Feb-19 | 134,443,983.00 |
4 | Widening, Strengthening, Construction of Hard Shoulder and Surfacing work from 46th(p) km to 60th Km along with construction of 2 Nos RCC Box Culvert with 1 No. Intersection of Ahladipur-Rajbari-Pangsha Kumarkhali-Kushtia (Chourhash) Road (R-710) under Road Division, Kushtia during the year 2017-2018. e_GP ID 120460. | RHD | GOB | Mar-18 | Mar-20 | 935,905,045.00 |
5 | Widening, Strengthening, Construction of Hard Shoulder and Surfacing work from 60th(p) km to 74th Km along with construction of 2 Nos RCC Box Culvert with 3 No. Intersection of Ahladipur-Rajbari-Pangsha Kumarkhali-Kushtia (Chourhash) Road (R-710) under Road Division, Kushtia during the year 2017-2018. e_GP ID 120461. | RHD | GOB | Mar-18 | Mar-20 | 831,871,147.00 |
6 | Construction of Connecting Road from Natore Road (RUET) to Rajshahi Bypass Road. Contract Package No.: RDA/RUETROAD/W/2017-2018/01. | Rajshahi Development Authority | GOB | Jan-18 | Dec-21 | 1,295,271,401.00 |
7 | Estimate for Earthwork, Reconstruction, Strengthening, DBS etc. pavement work, construction of Drain, protective work, sign signal installation work from Ch:-60+000m to Ch:- 88+790m of Comilla-Lalmai Chandpur-Laxmipur begumganj Road (R-140) under Road Division, Chandpur during the year 2016-2017. | RHD | GOB | Nov-17 | Aug-18 | 484,317,753.00 |
8 | Estimate for Earthwork, Reconstruction, Strengthening, DBS etc. pavement work, construction of Drain, protective work, sign signal installation work from Ch:-30+610m to Ch:- 60+000m of Comilla-Lalmai Chandpur-Laxmipur begumganj Road (R-140) under Road Division, Chandpur during the year 2016-2017. | RHD | GOB | Nov-17 | Aug-18 | 476,719,404.00 |
9 | Widening and Improvement of Road from ECB Chattar to Mirpur and Construction of Flyover at Kalshi Intersection Project. Phase-1 | RHD | GOB | Jun-23 | Dec-22 | 5,638,831,848.00 |
10 | Earthwork,widening, DBS etc pavement work construction of drainProtective work,Sign signal installation work from Chainage 109+000m to 129+000m of comilla-lalmai chandour lakshmipur-Begumganj road (R- 140) under Lakshmipur road division during the yaea 2016-17. | RHD | GOB | Jul-17 | Oct-18 | 667,526,673.00 |
11 | Construction of 1 x 104 ‘C’/’D’ type Qtr (14 storey with 14 storied foundation with basement floor, Car parking & other facilities in basement floor & ground floor) including ancillary Works for 17 Inf Div at Sylhet Cantt. | MES, | GOB | Jun-17 | May-19 | 565,083,376.00 |
12 | Rectification work of Joydevpur - Mymensingh Road Improvement Project, Package WI-3 (Ch. 30+250 km to 59+850 km) | SWO - | GOB | Nov-16 | Apr-17 | 773,718,967.00 |
13 | Construction of Premix Carpeting road from ‘B’ type Qtr bldg No. P-23 to Gun garage building No. P-19 with footpath cum drain, external electric line including ancillary works at Bangabandhu Cantt. | MES, | GOB | Jun-16 | Jul-17 | 113,731,303.00 |
14 | Contract No.: SASEC-RCP/lCB/W-01 (Lot No. WP-02): lmprovement of Road from Kaliakor Bypass intersection to Dulla Mari Road (18.00 km) from 2-Lane to 4-Lane including structures. Provision of support to project for third party maintenance quality check. | RHD | ADB & GOB | Dec-15 | Dec-21 | 10,588,415,010.45 |
15 | Internal Road, Drainage & Sewerage Network Development Project of Jolshiri Housing Sector-16 and Sector-17 | Bangladesh Army | GOB | Jan-21 | Dec-22 | 1,245,802,000.00 |
16 | Mohipal Flyover Construction Project at Feni | SWO - | GOB | Dec-15 | Jan-18 | 1,330,787,012.00 |
17 | Construction of Accommodation for 1 x 1200 Cadets (8-story with 8 storied foundation) including ancillary Works for BMA Bhatiary, Chittagong . | MES, | GOB | Jun-15 | Sep-20 | 2,480,000,000.00 |
18 | Construction of 1 x 152 ‘C’/’D’ type Qtr (20 storied foundation with basement floor, Car parking & other facilities in basement floor & ground floor) including ancillary Works for 17 Inf Div at Sylhet Cantt (1st phase) | MES, | GOB | Jun-15 | Nov-17 | 359,656,655.00 |
19 | Construction of 4-Lane Kalna Bridge (Nielsen Lohse Arch type) on AH1 along with Construction of Long Access Road and Installation of Toll Collection System with Toll Booths, Package No. A1 | RHD | JICA | Sep-18 | Aug-22 | 9,598,459,906.92 |
20 | Construction of 1 x SM Bk complex type ‘B’ (5 storey with 5 storied foundation) including internal/external services for East Regt at Dhaka Cantt. (Phase-2) (Group-1) | MES, | GOB | Jun-14 | Jun-15 | 307,873,467.00 |
21 | Mawa Approach Road and Selected Bridge End Facilities, ICB No. PMB/AR/02. | BBA | GOB | Jan-14 | Jul-16 | 1,911,265,691.00 |
22 | Construction of Service Area 2 under Padma Multipurpose Bridge Project, ICB No. PMB/SA/02 | BBA | GOB | Jan-14 | Jul-16 | 2,085,859,686.00 |
23 | Establishment of Shaheed Sayed Nazrul Islam Medical College and Hospital, Kishoregonj(SH: Construction of 5-Storied Hospital Building and Single Basement with 10-Storied Foundation including Civil, Sanitary & Electrical Work) | PWD | GOB | Dec-16 | Mar-17 | 1,766,837,850.00 |
24 | Construction of 4.010 km Road from Mowna Polli Biddut Zonal Office to Mowna Uttar Para Sub Package – 4 (Including Salna Overpass, Mowna Flyover Approach Road and Black Top of Sub Package – 2. | SWO - | GOB | Nov-13 | Sep-15 | 1,993,158,962.00 |
25 | Janjira Approach Road and Selected Bridge End Facilities under Padma Multipurpose Bridge Project, ICB No.: PMB/AR/01. | BBA | GOB | Oct-13 | Jun-17 | 13,389,899,518.00 |
26 | Construction of 1 x 110.00 Meter long Bridge including ancillary Works over lake from Sena Shahayak School to proposed JCO’s & OR’s residential area at Dhamalkot area Dhaka Cantt. (Phase 1, 2 & 3) | MES, | GOB | Jun-13 | Jun-15 | 367,661,789.00 |
27 | Construction of 1 x SM Bk complex type ‘B’ (5 storey with 5 storied foundation) including ancillary Works (Structure only) for East Regt at Dhaka Cantt. (Phase-1) (Group-1) | MES, | GOB | Mar-13 | Sep-14 | 361,364,921.00 |
28 | Sirajganj Hard Point (SHP): Strengthening of different sections for total length of 1934m in Upazila: Sirajganj, Contract No.: BWDB: WMIP FDR/BRE-SPL/W-04 | BWDB | WB & GOB | Jan-13 | Apr-15 | 804,977,603.00 |
29 | Land development, construction of Ansar barrak and barbed wire fencing at proposed 400/230/132 kV Substation at Kaliakoir, Gazipur under Bibiyana – Kaliakoir 400kV and Fenchugonj – Bibiyana 230kV Transmission Line Project | PGCB | GOB | Nov-12 | Mar-14 | 385,595,171.00 |
30 | Asphalt Concrete Overlay over the Runway at Hazrat Shahjalal International Airport, Kurmitola, Dhaka. | CAAB | GOB | Apr-12 | Dec-13 | 1,581,571,849.00 |
31 | Fael Khair Program: School-cum Cyclone Shelters, Contract No. BD1-0013 (Package 1). | IDB/ LGED | Fael Khair | Aug-11 | Jun-15 | 910,113,135.00 |
32 | Dredging work by cutter suction dredger for maintaining navigability of Mawa - Mangalmajhi - Charjanajat ferry and river route in the river Padma and Jamuna for the year 2011-2012, Lot-03. | BIWTA | GOB | Aug-11 | Jun-12 | 124,394,000.00 |
33 | Construction work of 112.61 (36.60X3) meter long PC girder bridge (Rajarhat Bridge) at 10th KM of Rangunia - Bangalhalia (Sukbilash) Road (Kalindee Rani Road) over Shilok River under Chittagong Road Division during the year 2010-2011. | RHD | GOB | Jun-11 | Dec-12 | 84,574,465.00 |
34 | Dredging of River Jamuna at Nalin Bazar, Upazila – Gopalpur, Tangail under Capital (Pilot) Dredging of River System in Bangladesh, Contract Package No. CDRSB-NB/Tang-01 | BWDB | GOB | Feb-11 | May-12 | 425,331,471.00 |
35 | Construction of road from Sultanpur to Akhaura check post. | RHD | Indian Private | Jan-11 | Jan-12 | 266,463,043.00 |
36 | Construction of Part 2 (Overpass & Link Bridge Portion – Alignment E and F) of the Flyover at Mirpur – Airport Road and Overpass at Banani Rail Crossing. | SWO - | GOB | Jan-11 | Dec-12 | 713,978,175.00 |
37 | Dredging work by cutter suction dredger for maintaining navigability of Narayangong - Daudkandi river route. | BIWTA | GOB | Oct-10 | Oct-11 | 117,551,605.00 |
38 | Construction of 515.12 Meter Long P.C. Girder Bridge over “Dhaleshwari River” at Elasin in Tangail at 39th KM of Aricha – Ghior – Daulatpur – Nagarpur – Tangail Road under Tangail Road Division, during the year 2008-2009. Contract Package No.: 03/SE/MRC/2008-2009 | RHD | GOB | Oct-09 | Apr-12 | 360,627,543.00 |
39 | Dredging work for maintaining navigability of Bhairab – Chatak river route in the river Surma and Baulai, Lot-01. | BIWTA | GOB | Sep-09 | Jun-10 | 46,600,000.00 |
40 | Construction of 4 laning of 4th (P) & 5th (P) km. at Dhaka - Narayangonj link road by widening of existing pavement under Narayangonj Road Division of RHD Road Circle Dhaka during the year 2008-2009. Ch. 3+700 to Ch. 5+000m = 1300m. | RHD | GOB | Jan-09 | Dec-09 | 74,245,526.00 |
41 | Dredging work for maintaining navigability of Mawa – Charjanajat ferry route, Lot-03. | BIWTA | GOB | Nov-08 | Feb-09 | 21,384,420.00 |
42 | Contract No. 3 under Road Improvement Component of Road Network Improvement and Maintenance Project-II (RNIMP-II): Reconstruction of (i) Parbatipur – Fulbari – Madhayapara and (ii) Boda – Debigonj – Domar – Nilphamari Road. | RHD | ADB & GOB | Jun-08 | Apr-12 | 1,786,173,931.00 |
43 | Periodic Maintenance Programme 2007- 08/DBST/Overlay/Both DBST & Overlay works (2nd Tranch), Package No. PMP-2007- 08/Overlay, Dhaka (Banani) - Joydevpur - Mymensingh. | RHD | GOB | Mar-08 | Nov-08 | 110,670,923.00 |
44 | Construction of PALS Road at Osmani International Airport, Sylhet | CAAB | GOB | Mar-08 | Sep-08 | 27,487,907.00 |
45 | Road Network Improvement and Maintenance Project-II, Contract Package No. PRMC RZ-1: Periodic Road Maintenance Work on Dhaka (Mirpur) – Utholia – Paturia – Natakhola – Kashinathpur – Bogra – Rangpur – Beldanga – Banglabandh Road (N5) Ch. 237+000 (Rahabal, Dist Gaibandha) to Ch. 278+000 (Pirgonj, Dist.- Rangpur) | RHD | ADB & GOB | Jan-08 | Apr-09 | 66,057,699.00 |
46 | Road Network Improvement and Maintenance Project-II, Contract Package No. PRMC RZ-4: Periodic Road Maintenance Work on Rangpur – Barobari – Kurigram Road (N506) Ch. 3+000 (Rangpur, Dist Rangpur) to Ch. 23+000 (Tista Bridge, Dist.- Rangpur) | RHD | ADB & GOB | Jan-08 | Apr-09 | 68,710,236.00 |
47 | Construction of Bank Rivetment work on the right bank of Jamuna River at Soilabari in Upazila - Sirajganj Sadar, District – Sirajganj, Contract No. RBS-07. | BWDB | GOB | Jan-08 | Dec-10 | 95,072,000.00 |
48 | Construction of Bank Rivetment work on the right bank of Jamuna River at Khokshabari in Upazila - Sirajganj Sadar, District – Sirajganj, Contract No. RBS-15. | BWDB | GOB | Jan-08 | Dec-10 | 85,800,000.00 |
49 | Construction of Bank Rivetment work on the right bank of Jamuna River at Ranigram in Upazila - Sirajganj Sadar, District – Sirajganj, Contract Package No. RBS-21 | BWDB | GOB | Jan-08 | Nov-10 | 72,207,048.00 |
50 | Construction of Bank Rivetment work on the right bank of Jamuna River at Ranigram in Upazila - Sirajganj Sadar, District – Sirajganj, Contract Package No. RBS-23 | BWDB | GOB | Jan-08 | Nov-10 | 74,176,374.00 |
51 | Contract No. PGCB/SA/2, Construction of 132 kV Shahjibajar – Ashugonj Transmission Line. | PGCB | GOB | Jan-08 | Aug-09 | 158,615,935.00 |
52 | Construction of Gulshan - Banani Arch Bridge (for connecting of Banani Road No. 11 with Gulshan Road No. 34, 35/A, 41 & 43) Project. | LGED | GOB | Sep-07 | Mar-09 | 254,100,000.00 |
53 | Improvement Component of Road Network Improvement and Maintenance Project-I (RNIMP-I), Contract No. 5: Reconstruction of Thakurgaon - Ranisankail Road. | RHD | ADB & GOB | Jun-07 | Jun-10 | 802,966,127.00 |
54 | Improvement Component of Road Network Improvement and Maintenance Project-I (RNIMP-I), Contract No. 4: Reconstruction of (i) Mithapukur - Madhayapara Road and (ii) Saidpur - Parbatipur Road. | RHD | ADB & GOB | Jun-07 | Mar-11 | 1,048,201,642.00 |
55 | Construction of Riverbank Slope Protection work by Placing & Dumping of Cement Concrete Blocks and Geo Bags from Penchakhola to Mohonganj at PIRDP, Contract No. JMREMP/P-7/2006 | BWDB | ADB & GOB | Mar-07 | Jun-08 | 84,705,256.00 |
56 | Construction of Riverbank Slope Protection work by Placing & Dumping of Cement Concrete Blocks and Geo Bags from Horirampur to Penchakhola at PIRDP, Contract No. JMREMP/P-6/2006 | BWDB | ADB & GOB | Mar-07 | Jun-08 | 97,191,741.00 |
57 | Development of Navigability by Dredging of Dilalpur-Markuli Sherpur-Jakigonj River Route, Group A-02, Lot No. 01 | BIWTA | GOB | Jan-07 | May-08 | 67,764,500.00 |
58 | Construction of 293.92m long PSC Girder Bridge over the Surma River on the Sylhet Gachbari-Kanaighat Bazar road at Kanaighat Bazar end. | LGED | GOB | Aug-06 | Apr-10 | 242,479,318.00 |
59 | Land development & boundary wall of Chapai – Nababgonj District Stadium at Chapai – Nababgonj, Package No. W1. | Bangladesh | GOB | Jun-06 | Dec-07 | 23,899,508.00 |
60 | Extension and Modernization of Passenger Terminal Building & Construction of 1st Floor of Osmani International Airport, Sylhet (S. H:- Civil, Water Supply & Sanitary, Internal Electrification, Refurbishment and other Allied Works) | CAAB | GOB | Apr-06 | Dec-08 | 227,138,310.00 |
61 | Jamuna Bridge Access Roads Project, Contract for Construction of Kaliakoir Bypass | RHD | JBIC & GOB | Mar-06 | May-08 | 702,581,244.00 |
62 | Construction of 366 meter long Pre Stressed concrete girder bridge (with steel arch) over the river Surma in Sylhet town near Kean Bridge at Kazibazar under Sylhet Road Division of Sylhet Road Circle, Sylhet during the year 2005-2006 | RHD | GOB | Feb-06 | Work Stopped | 358,387,280.00 |
63 | Periodic Maintenance Program 2005-2006, Contract No. PMP- 2005/09: Rangpur Bypass, Rangpur - Saidpur Road | RHD | GOB | Nov-05 | Dec-05 | 188,194,060.00 |
64 | Overlay with providing correcting course from 13th to 18th km of Banani - Tangail - Joydevpur Road under Dhaka Road Circle during the year 2005-2006 | RHD | GOB | Nov-05 | Dec-05 | 101,789,882.00 |
65 | Contract Package No. 23, Group No. 11, Land Development at Low Laying Area of Purbachal New Town Project. | RAJUK | GOB | Sep-05 | Aug-06 | 128,546,368.00 |
66 | Beautification Project, Contract No. 1: Widening and Beautification of Airport Road from Banani Rail crossing to North side of Mohakhali flyover. | Dhaka City | GOB | Aug-05 | Jun-07 | 125,553,718.00 |
67 | Development of Navigability by Dredging of Dilalpur-Markuli Sherpur-Jakigonj River Route, Group A-01, Lot No. 01 | BIWTA | GOB | Jul-05 | Feb-07 | 89,520,000.00 |
68 | Construction of Natore - Rajshahi 132 kV Transmission Line Project Contract No. PGCB/NR/1. | PGCB | GOB | Jul-05 | Oct-06 | 61,158,105.00 |
69 | Construction of Administrative building including sanitary, water supply and internal electrification works under "Establishment of a polytechnic Institute in Kishoregonj District", Lot No. 01. | Education | GOB | Jun-05 | Jun-06 | 24,541,656.00 |
70 | Construction of Female Hostel and Principal Quarter building including sanitary, water supply and internal electrification works under "Establishment of a polytechnic Institute in Kishoregonj District", Lot No. 04. | Education | GOB | Jun-05 | Jun-06 | 17,284,468.00 |
71 | Construction of Closure dam across the chute channel, River bank protection by concrete filled grout mattress & Engineer's site facilities at Koitola, Contract Package No. JMREMP/P-4/2005 | BWDB | ADB & GOB | Apr-05 | Jun-07 | 44,749,616.00 |
72 | Development of Osmani International Airport for Operation of Wide Body Aircraft, Sylhet. | CAAB | GOB | Mar-05 | Dec-07 | 1,035,751,909.00 |
73 | DFID Supported 2004-2005 Flood Damage Restoration Work, Contract No. DFID-DZ-2004-2005/10 | RHD | DFID | Mar-05 | Jun-05 | 75,097,880.00 |
74 | Strengthening of existing pavement of Sylhet - Fenchuganj - Rajnagar - Moulvibazar - Sree Mongal - Shaistaganj - Teliapara - Jagadishpur (with link to Sherpur) under Moulvi Bazar Road Division of Sylhet Road Circle, Contract No. 3/2004- 2005/SE/SRC. | RHD | GOB | Oct-04 | Apr-05 | 124,328,682.00 |
75 | Land Development at Low Laying Area of Purbachal New Town Project, Contract Package No. 25, Group No. 13. | RAJUK | GOB | Sep-04 | Jul-05 | 83,313,775.00 |
76 | Single Bituminous Surface Treatment (SBST) work at different location from 44 km to 142 km of Dhaka - Chittagong Highway (Daudkandi - Feni Portion) under Comilla Road Division, during the year 2003-2004, Tender No. 02/RCC/2003-2004. | RHD | GOB | May-04 | Oct-04 | 33,619,331.00 |
77 | Establishment of Mohila Polytechnic Institute at Khulna Divisional Head Quarter, Package No. KLN-1. | Education | GOB | Mar-04 | Sep-05 | 113,388,638.00 |
78 | Periodic Maintenance Program, Contract No. PMP-2003-2004/01: Tongi - Ashulia - EPZ Road, Banani - Tongi - Joydevpur Road, Station Feeder Road, Shahid Zaman Road. | RHD | GOB | Jan-04 | Nov-04 | 143,689,081.00 |
79 | Construction of Underpass at 2nd KM of Polder Road (Sanir Akhra) Ch. 1 + 500 m. to 2 + 000m under Narayangonj Road Division, Contract No. DRC/NRD/UP/2002-05 | RHD | GOB | Oct-03 | Jun-07 | 65,539,942.00 |
80 | Improvement of Three Inter District Bus Terminals under Dhaka Urban Transport Project, Contract No. (W)C5 | RHD | WB & GOB | Sep-03 | May-05 | 502,310,414.00 |
81 | Construction of 1x12'D' Type Officer's Quarter Building (14- storied) 4 flat in each floor, car parking in ground floor with other facilities. | MES, | GOB | Jun-03 | Apr-08 | 142,236,350.00 |
82 | Periodic Maintenance Program - 2002, Contract Package No. PMP/2002/11 Tongi Bridge to Joydevpur (Gazipur) | RHD | GOB | May-03 | Feb-04 | 41,067,213.00 |
83 | Periodic Maintenance Program 2002, Contract No. PMP- 2002/12: Bonpara - Walia, Walia - Dayarampur, Walia - Lalpur Road. | RHD | GOB | May-03 | Dec-03 | 37,191,335.00 |
84 | Jamuna Bridge Access Roads Project, Contract No. 1 (Remaining Works): Joydevpur to Gorai Section. | RHD | JBIC & GOB | Apr-03 | Mar-05 | 833,339,469.00 |
85 | Improvement of Roads at Demonstration Project Phase-II, Gabtoli Bus Terminal - Mirpur Mazar Road, Russel Square - Science Laboratory, Science Laboratory - Newmarket, Newmarket - Azimpur, Contract No. (W)C15A. | DCC | WB & GOB | Feb-03 | Sep-04 | 157,291,110.00 |
86 | Third Road Rehabilitation and Maintenance Project - Flood Component, 2000 Flood Damage Restoration Works, Contract No. 2000FDRW/R/04 | RHD | WB & GOB | Nov-02 | July-03 | 79,475,764.00 |
87 | Third Road Rehabilitation and Maintenance Project (RRMP-III). Improvement of Feeder Roads Type-A Contract No. F-24: Rangpur –Surdergonj - Gaibandha (Section–3). | RHD | WB & GOB | Aug-02 | Mar-05 | 211,025,126.00 |
88 | Third Road Rehabilitation and Maintenance Project (RRMP-III). Improvement of Feeder Roads Type-A Contract No. F-23: Rangpur –Surdergonj - Gaibandha (Section–2). | RHD | WB & GOB | Aug-02 | Mar-05 | 140,049,079.00 |
89 | Southwest Flood Damage Rehabilitation Project - 2000, Contract No. SWFDRP/KU/R/01 | RHD | ADB & GOB | Apr-02 | May-03 | 79,801,996.00 |
90 | Southwest Flood Damage Rehabilitation Project - 2000, Contract No. SWFDRP/KU/R/03 | RHD | ADB & GOB | Apr-02 | May-03 | 75,979,359.00 |
91 | Extension and Remodeling work of Hospital Building including Associate Works at Barisal General Hospital under HPPP, IDA Credit No. 3101-BD. Package No. W772-CMMU. | Construction | WB & GOB | Mar-02 | Feb-04 | 73,303,494.00 |
92 | Paksey Bridge Construction Project, Contract No. 2 (west connecting Road) | RHD | JBIC & GOB | Jun-01 | Jun-03 | 336,115,770.00 |
93 | Construction of 391.491m long Patgati Bridge at 19th KM of Pirojpur - Nazirpur - Matibhanga - Patgati - Gopalgonj road under Gopalgonj Road Division. | RHD | GOB | Jun-01 | Work Stopped | 160,888,504.00 |
94 | Periodic Maintenance Program - 2001, Contract Package No. PMP/2001/03 (Khulna-I), Jhenaidah - Kustia Road | RHD | GOB | Apr-01 | Apr-02 | 81,841,151.00 |
95 | Southwest Road Network Development Project (SRNDP), Contract No. 4: Bhatiapara Gopalgonj-Mollahat Road (including Gopalgonj By-pass). | RHD | ADB & GOB | Feb-01 | May-05 | 1,547,404,246.00 |
96 | Improvement of Feeder Roads Type - A under Third Road Rehabilitation & Maintenance Project, Sirajgonj - Kajipur Road, Contract No. F8 | RHD | WB & GOB | Aug-00 | Jan-03 | 300,020,310.00 |
97 | Improvement of Feeder Roads Type - A under Third Road Rehabilitation & Maintenance Project, Bagha-Lalpur-Ishwardi Road, Contract No. F9 | RHD | WB & GOB | Jul-00 | Dec-02 | 204,662,343.00 |
98 | Periodic Maintenance Program/2000, Contract No. PMP/2000/06: Katakhali - Bagherhat, Jessore - Chuknagar, Jessore - Chuknagar bypass and Chachra - Muruly bypass. | RHD | GOB | May-00 | Mar-01 | 72,360,926.00 |
99 | 98 FDR of Completed RIP Roads, Contract No. RIP-S1: Daudkandi to Start of Chandina Bypass (28.60 KM) and End of Chandina bypass to start of Comilla bypass (12.69 KM). | RHD | GOB | Mar-00 | Sep-00 | 64,832,374.00 |
100 | 98 FDR of Completed RIP Roads, Contract No. RIP-S2: End of Comilla bypass to Start of Comilla bypass. | RHD | GOB | Mar-00 | Sep-00 | 54,857,689.00 |
101 | 1998 Flood damage Restoration Project RRMP-II. Contract No. Rajbari - 1a of Faridpur Circle, Barisal Zone. | RHD | WB & GOB | Dec-99 | Dec-00 | 21,506,764.00 |
102 | 1998 Flood damage Restoration Project RRMP-II. Contract No. Rajbari - 1b of Faridpur Circle, Barisal Zone. | RHD | WB & GOB | Dec-99 | Dec-00 | 24,904,428.00 |
103 | Second Road Rehabilitation and Maintenance Project, 1998 Flood Damage Restoration Works, Contract No. F5 | RHD | IDA & GOB | Dec-99 | Dec-00 | 91,117,884.00 |
104 | 1998 Flood damage Restoration Project RRMP-II. Contract No. Bhola-1(one) Zone - Barisal. | RHD | WB & GOB | Aug-99 | Aug-00 | 17,425,320.00 |
105 | Widening and Improvement of Mirpur/Darus-Salam/ Mazar Shamoly Road, Contract Package No. A3 | DCC | WB & GOB | Aug-99 | Apr-03 | 448,534,869.00 |
106 | Second Road Rehabilitation and Maintenance Project, 1998 Flood Damage Restoration Works, Contract No. F4 | RHD | IDA & GOB | Apr-99 | Dec-00 | 322,785,872.00 |
107 | Widening and Improvement of Pragati Sarani Rampura Bridge to Airport Road, Contract Package No. A1 | DCC | WB & GOB | Mar-99 | Sep-02 | 335,297,473.00 |
108 | 1st Contract for Management, Operation and Maintenance of Jamuna Bridge, Toll Collection and Associated Works. | BBA | GOB | Jul-98 | Mar-04 | 1,174,500,000.00 |
109 | Construction of Road, Culvert, Footpath at Rajshahi City (Lakshmipur - Kasiadanga Road Project) | Rajshahi City | GOB | Jul-98 | Oct-01 | 98,202,359.00 |
110 | Second Road Rehabilitation & Maintenance Project. Periodic Maintenance Contract P18 Takerhat - Gopalgonj Road | RHD | WB & GOB | Apr-98 | Apr-99 | 83,251,421.00 |
111 | Construction of Syed Masud Rumi Bridge (Gorai Bridge) over Gorai River on 8th Km. of Kushtia – Rajbari Road | RHD | GOB | Dec-97 | Jun-05 | 222,245,567.00 |
112 | Jamuna Bridge Access Road Project, Contract No. 6: Dhaka (Mukti Sarani) to Daudkandi Road Section of Dhaka - Chittagong National Highway | RHD | ADB & GOB | Oct-97 | Dec-04 | 2,659,594,171.00 |
113 | Second Year Periodic Maintenance Programme, Contract No. P7: Jhenaidah - Chuadanga Township Road | RHD | WB & GOB | Jan-96 | Jan-97 | 220,000,000.00 |
114 | Periodic Maintenance Contract No. P6: Barisal - Swarupkati, Barisal - Jhalokati & Barisal - Patuakhali Road. | RHD | WB & GOB | Jan-96 | Jan-97 | 234,000,000.00 |
115 | Renovation and Upgradation of Hospital Building (RMCH) Rangpur. Package No. XX | Construction | ADB & GOB | Dec-94 | Oct-97 | 66,171,482.00 |
116 | Road Overlay and Improvement Project, Contract No. 7 (Eid Ghah - Ramu Road. | RHD | ADB & GOB | Nov-94 | Nov-97 | 343,521,000.00 |
117 | Road Rehabilitation and Maintenance Project Northwest Bangladesh, Phase-II, Contract No. 2/3A | RHD | WB & GOB | Jan-93 | Jun-96 | 330,767,428.00 |
118 | Road Improvement Project, Contract No. 8 (Ramu - Cox's Bazar Road. | RHD | ADB & GOB | Apr-92 | May-95 | 460,320,000.00 |
119 | Feeder Road Improvement Project Contract No. 12: Kishoregonj - Hossainpur Road (12.110 KM), Kishoregonj | RHD | ADB & GOB | Apr-92 | May-95 | 86,159,000.00 |
120 | Feeder Road Improvement Project Contract No. 11: Kishoregonj - Karimganj Road. | RHD | WB & GOB | Apr-92 | Oct-94 | 58,084,466.00 |
121 | Rehabilitation of East Flood Embankment, Contract No. 7 under Jamuna Multipurpose Bridge Authority | BBA | WB & GOB | Dec-90 | Aug-93 | 182,683,082.00 |
122 | Feeder Road Improvement Project Contract No. 10: Bhatkura - Basail Road. | RHD | WB & GOB | Aug-90 | Feb-93 | 108,292,337.00 |
123 | Road Improvement Project Rehabiliation and Resealing Component, Contract No. 14. | RHD | ADB & GOB | Nov-89 | Nov-92 | 239,860,000.00 |
124 | Construction of 100'-0" wide Kamalapur - Saidabad - Malibagh Road in Dhaka City. Construction of 100'0" wide Road Linking Airport Road and Green Road Called Panthapath in Dhaka City Reconstruction of Bangabandhu Road at Narayangonj. | RAJUK | GOB | Jul-87 | June-90 | 324,200,000.00 |
125 | Construction of Comilla - Chandina by Paass Road Project | RHD | WB & GOB | Jan-83 | Feb-87 | 120,871,000.00 |
126 | Khulna Mongla Road Construction Project | RHD | ADB & GOB | Jun-80 | Jun-85 | 250,000,000.00 |